QSR Cable and Network Installation Project

QSR

FACTS:

• Timeline: 6 Months
• Deployment Sites: 750+
• East to West Coast Coverage

SCOPE OF WORK:

• Run and secure new Cat 5e pre-connectorized cable drop between the switch and the Dell Wyse Thin Client per Standards. Do not lay cable on top of drop ceiling or light fixtures. Use existing cable route and secure to it.
• Install new Down Rod and mounting brackets for ELO Display, Bump Bar and Dell Wyse Thin Client. Make sure there are trusses to properly secure the Uni-Strut and Down Rod.
• Run and secure all cables for the Dell Wyse Thin Client, ELO Display and Bump Bar referencing Installations Guide – make sure to provide neat cable management.
• Install new dedicated Isolated ground Twist Lock Quad Box per local and NECA codes.
• Power up Dell Wyse Thin Client and ELO Display. Make sure to use the 19v power supply for the Dell Wyse Thin Client and 12v power supply for the ELO Display.
• If applicable, bring on-line Back-up Switch.
• Ability to turn-up HOTG Display using Restaurant Builder – reference Installation Guidelines. Must have Credentials to login.
• Test and validate operational functionality with Local Contact. Have local contact submit an order for ¼ lb. fresh meat order from existing POS. You will see it display and hear an audible tone.
• If applicable, work with Technical Support. If instructed, Re-Image Dell Wyse Thin Client using the 64K 3.0 USB Thumb drive with PR7 v4.5 image, wireless keyboard and mouse.
• Take Final Pictures, fill out Technician Checklist, Sign-Off and email to ICC.